For example, the pull-
ing force for conductor having cross section 1.wago.6
www.75
20
18
20
30
20
30
20
30
1
1. During the test, the
conductor must neither slip out the clamping unit, nor break near the clamping unit.com
WAGO Rail-Mount Terminal Block Systems
Technical Information
Mechanical Tests (continued)
Tests and Testing Procedures per IEC/EN Standards (continued)
• Pull-Out Test per IEC/EN 60947-7-1, IEC/EN 60998-2-2, IEC/EN 60999-1
Conductor Pull-Out Forces
The clamping units screwless terminal
blocks must withstand the pull-out forces as
follows:
IEC 60947-1/EN 60947-1/VDE 0660‑100,
Table 5:
Low-voltage switchgear and controlgear,
General rules
IEC 60947-7-1/EN 60947-7-1/
VDE 0611-1, Rail-mount terminal blocks for
copper conductors
IEC 60998-2-1/EN 60998-2-1/
VDE 0613-2-1, Table 104:
IEC 60998-2-2/ 60998-2-2
VDE 0613-2-2, Table 103:
Connecting devices for low-voltage circuits
for household and similar purposes
Particular requirements for connecting
devices separate entities with screw-
clamp screwless terminal blocks.5 mm² (16 AWG) and 100 for conductor with cross section mm²
(6 AWG). The larger the cross section the conductor, the higher the pull-out force that selected.5
4
14
12
50
60
50
60
50
60
6
10
10
8
80
90
80
90
80
90
16
25
6
4
100
135
100
135
100
135
–
35
3
2
156
190 190 190
–
50
1
1/0
236
236 236
70
95
2/0
3/0
285
351
285
351
–
120
4/0
250
427
427
427
427
150
185
300
350
427
503
427
503
–
240
400
500
503
578
503
578
300 600 578 578
.
Rated
Cross-
Section
Pull-Out Forces per IEC/EN
60947-7-1 60998-2-2 60999-1/-2
mm² AWG/kcmil N
0. The values specified these standards are the same for both screw clamp and spring clamp terminal blocks.34
24
22
10
15
10
15
10
15
0. The pulling force selected according
to the cross-sectional area.5
–
16
35
40
35
40
35
40
2.2
0.
During the test, pulling force applied without jerking, for one minute, the connected conductor.5
0.
IEC 60999-1/EN 60999-1/VDE 0609-1, Table
3:
IEC 60999-2/EN 60999-2/VDE 0609‑101,
Table 2:
Safety requirements for screw-clamp and
screwless clamping units for electrical cop-
per conductors
The pull-out test simulates the mechanical stress the clamping unit when, for example, the installer pushes the conductor aside better
access/operate the adjacent clamping unit, verifies the conductor connected properly briefly pulling it