Basic Electrical Installation Work

| Kategorie: Kniha  |

Strana 361 z 399

Jak získat tento dokument?






Poznámky redaktora
Carry out functional testing (e. operation RCDs). If any test fails comply with the Regulations, then all the preceding tests must repeated after the fault has been rectified. Safety First Working live ● Never work‘live’ ● Some‘live testing’is allowed by competent persons ● Otherwise, isolate and secure the isolation ● Prove the supply‘dead’before starting work. Test for polarity using the continuity method.g. . The checklist guide, not exhaustive detailed, and should used to identify relevant items for inspection, which can then expanded upon.1 and the Site Guide for rea- sons safety and accuracy. Recheck polarity using voltmeter approved test lamp. 5. 3. Those tests which are relevant the installation must then carried out in the sequence given Regulation 612. This because the ear- lier test results may have been influenced the fault (Regulation 612. For example, the first item the checklist, connection conduc- tors, might further expanded include the following: ● Are connections secure? ● Are connections correct? (conductor identification) ● the cable adequately supported that strain placed the connections? ● Does the outer sheath enter the accessory? ● the insulation undamaged? ● Does the insulation proceed but not into the connection? This repeated for each appropriate item the checklist. Test for insulation resistance. 8. Test the earth fault loop impedance.Basic Electrical Installation Work 350 ● choice and setting protective devices ● labelling circuits, fuses, switches and terminals ● selection equipment and protective measures appropriate to external influences ● adequate access switchgear and equipment ● presence danger notices and other warning notices ● presence diagrams, instruction and similar information ● appropriate erection method. With the supply connected 6. 2. Test the continuity all ring final circuit conductors. 7.1). Test for continuity protective conductors, including protective equipotential and supplementary bonding. Test the earth electrode resistance. These tests are follows: Before the supply connected 1. 4