TOPJOB® S
Implementing Current and Voltage Transformer Circuit
. required, external voltage can applied to
the measuring device via the test socket.wago.99
1
2
Conductor entry
Test socket
Jumper slot for 282-43x jumper
Jumper slot for 2007-844x circuit jumper
2007-844x circuit jumper
1
2
~
Conductor entry
Test socket
Jumper slot for 282-43x jumper
Jumper slot for 2007-844x circuit jumper
2007-844x circuit jumper
1
2
Conductor entry
Test socket
Jumper slot for 282-43x jumper
Jumper slot for 2007-844x circuit jumper
2007-844x circuit jumper
1
2
A
Conductor entry
Test socket
Jumper slot for 282-43x jumper
Jumper slot for 2007-844x circuit jumper
2007-844x circuit jumper
www.
Disconnect link shorting position II
Test current measurement: Disconnect link measuring
position III
The measuring device electrically disconnected from the transformer.
The transformer not disconnected from the measuring device yet, the shorting path activated moving the discon-
nect link into shorting position and the transformer safely shorted.com
Rail-Mount Terminal Blocks, TOPJOB® S
Rail-Mount Terminal Blocks, TOPJOB® S
Disconnect link operating position I
Terminal blocks required:
2 disconnect/test terminal block (2007‑8821)
1 circuit jumper, orange (2007-8442)
Locking covers interlocking links (option)
In the operating position, the measurement device connected the transformer, the circuit jumper inserted and the
disconnect link position I.
Measurement testing (using both test sockets)
Terminal block Disconnect link operating position I
Terminal block Disconnect link measuring position III
Measurement testing: First insert the reference current meter (A) into the test socket, then move the disconnect link into
measurement point III (test current measurement)