Medium voltage DC (MVDC) grids for an all-electric society

| Kategorie: Firemní tiskovina  |

Vydal: Neurčeno Autor: Tým odborníků IEC

Strana 71 z 90

Jak získat tento dokument?






Poznámky redaktora
1 Distribution submarine cable First scenario: existing submarine cable is converted realize additional operating capacity, avoiding investment new cable installation, shown Figure A-1.71 Annex Case studies MVDC economics A. Therefore, integrating a 30 MVA distributed generator load would require two distribution lines.62 km. The latter outcome due to the maintenance costs the converters. In this scenario, the maximum continuous operating capacity the high-capacity 22. When looking the 20-year operational net present value (NPV), the break-even length increases to 4. Figure A-2 shows the investment cost comparison for and distribution lines at various submarine cable lengths.9 AC distribution line MVA. Converting the system to DC ±35 kV, however, doubles the capacity: single DC line can accommodate additional generation load, resulting investment savings.42 km, slightly less favourable than the initial investment analysis. The construction cost of a submarine cable assumed approximately USD 264/km. Figure A-1 MVDC replacement for submarine cable scenario Figure A-2 Submarine cable MVDC economics based initial investment (left) and 20-year operational NPV (right) 0 5 11 16 21 26 32 37 42 7 10 12 15 18 20 23 25 28 0 10 20 30 40 50 0 8 USD(M$) FEEDER LENGTH (KM) Initial Investment Cost AC Investment Cost DC Investment Cost 0 6 12 18 25 31 37 43 49 14 17 20 23 26 29 32 35 38 0 10 20 30 40 50 60 1 8 USD(M$) FEEDER LENGTH (KM) 20-Year NPV NPV DC NPV . Based initial investment costs, MVDC achieves an economic advantage over MVAC submarine cable length approximately 2. Because distribution lines require rectifiers and inverters both ends, the benefits of conversion increase with the length the submarine cable section