Medium voltage DC (MVDC) grids for an all-electric society

| Kategorie: Firemní tiskovina  |

Vydal: Neurčeno Autor: Tým odborníků IEC

Strana 71 z 90

Jak získat tento dokument?






Poznámky redaktora
Therefore, integrating a 30 MVA distributed generator load would require two distribution lines. Because distribution lines require rectifiers and inverters both ends, the benefits of conversion increase with the length the submarine cable section.62 km.9 AC distribution line MVA. In this scenario, the maximum continuous operating capacity the high-capacity 22. Converting the system to DC ±35 kV, however, doubles the capacity: single DC line can accommodate additional generation load, resulting investment savings.1 Distribution submarine cable First scenario: existing submarine cable is converted realize additional operating capacity, avoiding investment new cable installation, shown Figure A-1. Figure A-2 shows the investment cost comparison for and distribution lines at various submarine cable lengths. The latter outcome due to the maintenance costs the converters. The construction cost of a submarine cable assumed approximately USD 264/km. Based initial investment costs, MVDC achieves an economic advantage over MVAC submarine cable length approximately 2.42 km, slightly less favourable than the initial investment analysis. Figure A-1 MVDC replacement for submarine cable scenario Figure A-2 Submarine cable MVDC economics based initial investment (left) and 20-year operational NPV (right) 0 5 11 16 21 26 32 37 42 7 10 12 15 18 20 23 25 28 0 10 20 30 40 50 0 8 USD(M$) FEEDER LENGTH (KM) Initial Investment Cost AC Investment Cost DC Investment Cost 0 6 12 18 25 31 37 43 49 14 17 20 23 26 29 32 35 38 0 10 20 30 40 50 60 1 8 USD(M$) FEEDER LENGTH (KM) 20-Year NPV NPV DC NPV .71 Annex Case studies MVDC economics A. When looking the 20-year operational net present value (NPV), the break-even length increases to 4