Open the circuit-breaker, turn the key and
remove from its seat.
Close the circuit-breaker.
The locks function correctly.
The circuit-breaker opens.
Racking-in operation: the circuit-breaker racks
in correctly.
The signals due the relative operations are
given correctly.
Supply the spring loading geared motor the
corresponding rated voltage.
Carry out the operating tests. Supply the undervoltage release the
corresponding rated voltage (if any).
Note.
Supply the shunt opening release the
corresponding rated voltage.
The signals are correct.
Insertthe auxiliary contacts suitable signalling
circuits.
S upply the undervoltage release the
corresponding rated voltage and carry out the
circuit-breaker closing operation. Interlocking
devices between circuit-breakers side by
side and one top another (if any)
10 For withdrawable circuit-breakers: racking
-in/out device
P re
Carry out some opening and closing operations
(see the chapter 7.
ite d
1 Manual operating mechanism
2 Geared motor (if any)
3 Undervoltage release
(if any)
4 Shunt opening release (if any)
5 Shunt closing release (if any)
6 Circuit-breaker lock the open position
(with key padlocks)
7 Auxiliary contacts the circuit-breaker
8 Auxiliary contacts for signalling circuit-
breaker connected, test isolated and
disconnected
9 Lock vice circ it-b rs
connected and disconnected.
15/158
.
The signals are given correctly.
C arry som sin and ning
operations.
The circuit-breaker opens correctly. The signals
are correct.2).
Supply the shunt closing release its rated
voltage.
Both anual and electrical closing are
prevented.
P itiv ck
The spring loading lever moves correctly.
S upply the undervoltage release the
corresponding rated voltage and carry out the
circuit-breaker closing operation.
The geared motor reloads the springs after
each closing operation.1 eneral s
- Check tightness the power connections the circuit-breaker terminals
- Carry out all the preparatory operations the release
- Make sure that the value the auxiliary circuit power supply voltage between and 110% the rated voltage the electrical applications
- Make sure that there adequate air circulation the place installation avoid overheating
- Also carry out the checks specified the following table. Attempt circuit-breaker
closing operation.
Insertthe auxiliary contacts suitable signalling
circuits.
Disconnect voltage the release. The signals
are correct. Carry out some circuit-breaker closing
and opening operations. The signal changes
over.
Open the circuit-breaker. The first turns the crank handle
do not meet with particular resistance.
The circuit-breaker closes correctly.
Carry out some racking-in and out operations.
CAUTION
When there undervoltage release, the
circuit-breaker can only closed after the
release has been electrically energized.
The springs are loaded correctly.
The geared otor stops with the springs
loaded.Putting into service
6.
The circuit-breaker closes correctly. The
signals are correct.
Model 2234 Apparatus Scale
L 2778
Doc-Na 1SDH000460R0002
Page No. Then put the circuit-breaker the
connected, test isolated and disconnected
position