ABB Vzduchové jističe EMAX E1-E6 Montážní návody a manuály (03)

| Kategorie: Návody k obsluze Montážní návody  | Tento dokument chci!

Vydal: ABB s.r.o, ELSYNN Autor: ABB ELSYnn

Strana 172 z 660

Vámi hledaný text obsahuje tato stránku dokumentu který není autorem určen k veřejnému šíření.







Poznámky redaktora
The circuit-breaker opens. Note.Putting into service 6. Open the circuit-breaker. Close the circuit-breaker. Carry out some circuit-breaker closing and opening operations. Attempt circuit-breaker closing operation.1 eneral res - Check tightness the power connections the circuit-breaker terminals - Carry out all the preparatory operations the release - Make sure that the value the auxiliary circuit power supply voltage between and 110% the rated voltage the electrical applications - Make sure that there adequate air circulation the place installation avoid overheating - Also carry out the checks specified the following table. The signals are correct. Supply the shunt closing release its rated voltage. Supply the undervoltage release the corresponding rated voltage (if any). Item inspected 1 Manual operating mechanism 2 Geared motor (if any) 3 Undervoltage release (if any) 4 Shunt opening release (if any) 5 Shunt closing release (if any) 6 Circuit-breaker lock the open position (with key padlocks) 7 Auxiliary contacts the circuit-breaker 8 Auxiliary contacts for signalling circuit- breaker connected, test isolated and disconnected 9 vice irc it-b rs connected and disconnected. S upply the undervoltage release the corresponding rated voltage and carry out the circuit-breaker closing operation. Carry out some racking-in and out operations. The circuit-breaker opens correctly. The signals are correct. Insert the auxiliary contacts suitable signalling circuits. The circuit-breaker closes correctly. The geared motor reloads the springs after each closing operation. Insert the auxiliary contacts suitable signalling circuits. C arry som sin and g operations. Then put the circuit-breaker the connected, test isolated and disconnected position. Disconnect voltage the release. Supply the spring loading geared motor the corresponding rated voltage. The signals are correct.2). Carry out the operating tests. CAUTION When there undervoltage release, the circuit-breaker can only closed after the release has been electrically energized. The signals are given correctly. Racking-in operation: the circuit-breaker racks in correctly. 14/1 08 . Both anual and electrical closing are prevented. The geared motor stops with the springs loaded. Positive check The spring loading lever moves correctly. Model L3447 A pparatus Emax DC S cale D oc-N 1SDH000635R0002 Page No. Supply the shunt opening release the corresponding rated voltage. The springs are loaded correctly. The locks function correctly. Interlocking devices between circuit-breakers side by side and one top another (if any) 10 For withdrawable circuit-breakers: racking -in/out device Procedure Carry out some opening and closing operations (see the chapter 7. The signal changes over. The first turns the crank handle do not meet with particular resistance. The signals due the relative operations are given correctly. S upply the undervoltage release the corresponding rated voltage and carry out the circuit-breaker closing operation. Open the circuit-breaker, turn the key and remove from its seat. The signals are correct. The circuit-breaker closes correctly