Poznámky redaktora
Carry out the operating tests. The signals are correct. The springs are loaded correctly. The circuit-breaker opens.Putting into service 6. The signals due the relative operations are given correctly. The locks function correctly. Insert the auxiliary contacts suitable signalling circuits. Open the circuit-breaker. The circuit-breaker opens correctly. Item inspected 1 Manual operating mechanism 2 Geared motor (if any) 3 Undervoltage release (if any) 4 Shunt opening release (if any) 5 Shunt closing release (if any) 6 Circuit-breaker lock the open position (with key padlocks) 7 Auxiliary contacts the circuit-breaker 8 Auxiliary contacts for signalling circuit- breaker connected, test isolated and disconnected 9 vice irc it-b rs connected and disconnected. Both anual and electrical closing are prevented. Supply the shunt closing release its rated voltage. The geared motor reloads the springs after each closing operation. Then put the circuit-breaker the connected, test isolated and disconnected position. The circuit-breaker closes correctly. Supply the shunt opening release the corresponding rated voltage. Note. The signals are correct. Carry out some racking-in and out operations. The signals are given correctly. S upply the undervoltage release the corresponding rated voltage and carry out the circuit-breaker closing operation. Carry out some circuit-breaker closing and opening operations. S upply the undervoltage release the corresponding rated voltage and carry out the circuit-breaker closing operation. Model L3447 A pparatus Emax DC S cale D oc-N 1SDH000635R0002 Page No. C arry som sin and g operations. The signal changes over.2). The first turns the crank handle do not meet with particular resistance. Supply the undervoltage release the corresponding rated voltage (if any). The circuit-breaker closes correctly. The signals are correct. 14/1 08 . The geared motor stops with the springs loaded. Open the circuit-breaker, turn the key and remove from its seat. Attempt circuit-breaker closing operation. Racking-in operation: the circuit-breaker racks in correctly. The signals are correct. CAUTION When there undervoltage release, the circuit-breaker can only closed after the release has been electrically energized.1 eneral res - Check tightness the power connections the circuit-breaker terminals - Carry out all the preparatory operations the release - Make sure that the value the auxiliary circuit power supply voltage between and 110% the rated voltage the electrical applications - Make sure that there adequate air circulation the place installation avoid overheating - Also carry out the checks specified the following table. Interlocking devices between circuit-breakers side by side and one top another (if any) 10 For withdrawable circuit-breakers: racking -in/out device Procedure Carry out some opening and closing operations (see the chapter 7. Close the circuit-breaker. Supply the spring loading geared motor the corresponding rated voltage. Insert the auxiliary contacts suitable signalling circuits. Disconnect voltage the release. Positive check The spring loading lever moves correctly